| title: Go-Release-Cycle |
| --- |
| |
| This wiki page is maintained by the Go team. Please |
| [send comments to golang-dev](https://groups.google.com/group/golang-dev) or |
| [file issues](https://go.dev/issue) instead of making changes directly. |
| |
| Short link: https://go.dev/s/release. |
| |
| ## Overview |
| |
| Go is released every six months. Each release cycle is broken down into a |
| development phase lasting about 4 months, followed by a 3-month period of |
| testing and polishing called the release freeze. If everything goes well, work |
| on the next release begins before the previous release has shipped, resulting in |
| an overlap of about a month. |
| |
| After the initial release of a version, it is supported with minor releases that |
| fix severe bugs and security issues. |
| |
| ## Timeline |
| |
| The current release cycle is aligned to start in mid-January and mid-July of |
| each year. The target milestones for a release cycle are as described below. We |
| try to hit the targets as closely as possible, while still delivering a quality |
| release. |
| |
| To give the team time to prepare, and to address unexpected problems, we prefer |
| to do release work early or mid-week. That means that exact dates will vary year |
| to year, so milestones are specified as weeks in a particular month. Week 1 is |
| the week starting on the first Monday of the month. All dates are subject to |
| change based on the year's holiday timings. |
| |
|  |
| |
| #### January / July week 1: Planning for release begins. |
| |
| Planning of major work for upcoming release cycle is announced on |
| [golang-dev](https://groups.google.com/group/golang-dev). |
| |
| Example: [Go 1.20](https://groups.google.com/g/golang-dev/c/V8ez4YunkeE) |
| |
| #### January / July week 3: Release work begins. |
| |
| Once the prior release has entered its final stabilization period, the tree |
| opens for general development. All kinds of development are welcome during this |
| period. It's preferable for large or particularly risky changes to land well |
| before the end of the development window, so that there's time to fix any |
| problems that arise with them. |
| |
| #### May / November week 4: Release freeze begins. |
| |
| This milestone begins the second part of the release cycle, the release freeze. |
| The release freeze applies to the entire main repository as well as to the code |
| in subrepositories that is needed to build the binaries included in the release, |
| particularly vet and all its dependencies in the tools subrepository. |
| |
| During the freeze, only bug fixes and doc updates are accepted. On occasion new |
| work may be done during the freeze, but only in exceptional circumstances and |
| typically only if the work was proposed and approved before the cutoff. Such |
| changes must be low risk. See [freeze exceptions](#freeze-exceptions) below. |
| |
| This part of the release cycle is focused on improving the quality of the |
| release, by testing it and fixing bugs that are found. However, every fix must |
| be evaluated to balance the benefit of a possible fix against the cost of now |
| having not as well tested code (the fix) in the release. Early in the release |
| cycle, the balance tends toward accepting a fix. Late in the release cycle, the |
| balance tends toward rejecting a fix, unless a case can be made that the fix is |
| both low risk and high reward. |
| |
| Examples of low risk changes appropriate late in the cycle include changes to |
| documentation and fixes to new features being introduced in the current release |
| (since there is no chance of introducing a regression compared to an earlier |
| release). |
| |
| Shortly after the freeze begins, nearly all known bugs should have been fixed or |
| explicitly postponed (either to the next release or indefinitely). The remainder |
| should usually be tracked as release blockers and worked on urgently. |
| |
| #### June / December week 2: Release candidate 1 issued. |
| |
| A release candidate is meant to be as close as possible to the actual release |
| bits. Issuing a release candidate is an indication that the Go team has high |
| confidence that the tree is free of critical bugs. In particular, because Google |
| continuously tracks the development version of Go, by the time a release |
| candidate is issued, a close approximation of it will have been running in |
| production at Google for at least a week or two. |
| |
| Once a release candidate is issued, only documentation changes and changes to |
| address critical bugs should be made. In general the bar for bug fixes at this |
| point is even slightly higher than the bar for bug fixes in a minor release. We |
| may prefer to issue a release with a known but very rare crash than to issue a |
| release with a new but not production-tested fix. |
| |
| If critical bugs are reported and fixed, additional release candidates may be |
| issued, but typically not more than one every two weeks. |
| |
| Again, a release candidate is meant to be bug-free, as much as possible. |
| Organizations are encouraged to deploy it in production settings after |
| appropriate organization-specific testing. |
| |
| The calm period between a release candidate and the final release is a good time |
| for additional testing or for discussing the next release (see the planning |
| milestone above). |
| |
| #### July / January week 3: Work on the next release begins |
| |
| While the current release is being stabilized, the tree reopens for work on the |
| next. During this period, fixes intended for the current release need to be |
| [cherry-picked onto the release branch](https://go.dev/wiki/MinorReleases#making-cherry-pick-cls). |
| Unlike cherry-picks for minor releases, these changes don't need a backport |
| issue and don't need to be approved by the release team. As long as they're |
| permitted by the [freeze policy](#may--november-week-4-release-freeze-begins), |
| they can be reviewed and submitted like any other CL. |
| |
| #### August / February week 2: Release issued. |
| |
| Finally, the release itself! |
| |
| A release should not contain significant changes since the last release |
| candidate: it is important that all code in the release has been well tested. |
| Issuing a release is an indication that release testing has confirmed the |
| release candidate's high confidence that the tree is free of critical bugs. |
| |
| Even if a release goes smoothly and there's spare time, we prefer to stay on |
| schedule. Extra testing can only improve the stability of a release, and it also |
| gives developers working on the Go release more time to think about and plan the |
| next release before code changes start pouring in again. |
| |
| By the time of the final release, Google will have been using this version of Go |
| for nearly two months. While Google's successful use does not guarantee the |
| absence of problems, our experience has been that it certainly helps improve the |
| quality of the release. We strongly encourage other organizations to test |
| release candidates as aggressively as they are able and to report problems that |
| they find. |
| |
| Once a release is stabilized, work on the next release, including code reviews |
| and submission of new code, can begin, and the cycle repeats. Note that if a |
| release is delayed, work on the next release may be delayed as well. |
| |
| ## Release Maintenance |
| |
| A minor release is issued to address one or more critical problems for which |
| there is no workaround (typically related to stability or security). The only |
| code changes included in the release are the fixes for the specific critical |
| problems. Important documentation-only changes and safe test updates (such as |
| disabling tests), may also be included as well, but nothing more. Minor releases |
| preserve backwards compatibility as much as possible, and don't introduce new |
| APIs. |
| |
| Minor releases to address problems (including security issues) for Go 1.x stop |
| once Go 1.x+2 is released. For more about security updates, see the |
| [security policy](https://go.dev/security). |
| |
| See also the [MinorReleases](https://go.dev/wiki/MinorReleases) wiki page. |
| |
| ## Freeze Exceptions |
| |
| Fix CLs that are |
| [permitted by the freeze policy](#may--november-week-4-release-freeze-begins) do |
| not need a freeze exception. |
| |
| Any exceptions to the freeze must be communicated to and explicitly approved by |
| the Go Release Team before the freeze. If you’d like to request an exception, |
| please file an issue in the issue tracker with "[freeze exception]" as a suffix |
| and include "CC @golang/release" ([example](https://go.dev/issue/42747)). We |
| will address any requests on a case-by-case basis with a strong preference for |
| not permitting changes after the freeze. |
| |
| ## Historical note |
| |
| A version of this schedule, with a shorter development window, was originally |
| adopted for the Go 1.7 release in 2016. After years of difficult releases, |
| testing and process improvements in 2022 and 2023 led to a timely 1.19 release. |
| For 1.20, the development window was expanded with a late freeze and early thaw. |
| These changes were formalized for the 1.21 release. We anticipate continuing to |
| ship on time. |
| |